Question #: 1300
Topic #: 1
[All PMP Questions]

A project stakeholder has expressed concern that the established success criteria for the project are not being met. What should the project manager do next?

  • A. Document the agreed-upon ownership of benefits realization.
  • B. Review the established project benefits tracking metrics.
  • C. Create a project benefits management plan.
  • D. Update the project business case document.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: B
B. Review the established project benefits tracking metrics
upvoted 1 times
...
ELTIGANI
5 months, 3 weeks ago
Selected Answer: B
B. Review the established project benefits tracking metrics. Here's why: Assessment of Performance: Reviewing the established project benefits tracking metrics allows the project manager to assess whether the project is meeting its success criteria and delivering the expected benefits. This step helps identify any discrepancies between the planned benefits and the actual outcomes. Data-Driven Analysis: By examining the project benefits tracking metrics, the project manager can gather data on the project's performance against the established success criteria. This data-driven analysis provides insights into areas where the project may be falling short and helps in determining appropriate corrective actions. Immediate Action: Reviewing the metrics provides an immediate response to the stakeholder's concern and demonstrates proactive management of project performance. It allows the project manager to address the stakeholder's concerns based on factual information rather than assumptions.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...