exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1299 discussion

Actual exam question from PMI's PMP
Question #: 1299
Topic #: 1
[All PMP Questions]

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget.

What should the project manager have done at the start of the project?

  • A. Managed the team as necessary and allowed them to work on their own
  • B. Adapted a direct management style according to the project team's needs
  • C. Established goals and provided the project team with sufficient authority to work
  • D. Adapted a servant leader management style to support the team's development
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PRASAD180
4 days, 12 hours ago
B is correct
upvoted 1 times
...
Okstm
4 months ago
Selected Answer: B
The project manager should have adapted a direct management style initially to provide the necessary structure, guidance, and support that a newly hired team needs to perform effectively. This would have mitigated delays and budget overruns by fostering clear expectations and active oversight from the start.
upvoted 1 times
...
victory108
5 months, 3 weeks ago
Selected Answer: B
B. Adapted a direct management style according to the project team's needs
upvoted 1 times
...
c8ee0e6
8 months, 3 weeks ago
Selected Answer: B
In this scenario direct management style is the best. (B)
upvoted 1 times
...
ELTIGANI
9 months, 4 weeks ago
Selected Answer: C
C. Established goals and provided the project team with sufficient authority to work
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago