Question #: 1299
Topic #: 1
[All PMP Questions]

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget.

What should the project manager have done at the start of the project?

  • A. Managed the team as necessary and allowed them to work on their own
  • B. Adapted a direct management style according to the project team's needs
  • C. Established goals and provided the project team with sufficient authority to work
  • D. Adapted a servant leader management style to support the team's development
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: B
B. Adapted a direct management style according to the project team's needs
upvoted 1 times
...
c8ee0e6
4 months, 2 weeks ago
Selected Answer: B
In this scenario direct management style is the best. (B)
upvoted 1 times
...
ELTIGANI
5 months, 3 weeks ago
Selected Answer: C
C. Established goals and provided the project team with sufficient authority to work
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.