Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1292 discussion

Actual exam question from PMI's PMP
Question #: 1292
Topic #: 1
[All PMP Questions]

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do?

  • A. Ask the sponsor to close the project and pay the contracted penalty.
  • B. Meet with the sponsor to ask for their support.
  • C. Check with the team to learn what can be done, and consult an expert.
  • D. Check that this information was documented correctly.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amirov
3 weeks, 4 days ago
Selected Answer: D
why would I assume that the stakeholder information about this information being documented in a lesson learned is CORRECT, I'd rather check first :) I go with D
upvoted 1 times
...
victory108
1 month, 2 weeks ago
Selected Answer: C
C. Check with the team to learn what can be done, and consult an expert
upvoted 1 times
...
27b2ada
3 months, 1 week ago
Selected Answer: D
i go with D
upvoted 1 times
...
sidje
3 months, 3 weeks ago
Selected Answer: C
Cette action permet de comprendre en profondeur le problème, d'explorer les solutions possibles et de préparer une recommandation bien informée pour la suite des événements. Une fois toutes les informations recueillies, le chef de projet pourra alors impliquer le parrain et d'autres parties prenantes de manière constructive.
upvoted 1 times
...
martinx84
4 months ago
Selected Answer: D
Check that this information is documented
upvoted 1 times
...
ELTIGANI
5 months, 3 weeks ago
Selected Answer: C
C. Check with the team to learn what can be done, and consult an expert.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...