Actual exam question from PMI's PMI-SP
Question #: 10
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

  • A. It means the largest schedule variance you can have is five percent.
  • B. It is the earned value divided by the planned value for your project.
  • C. It is the expectation of management to be 95 on schedule at 95 percent of the project.
  • D. It means you will need to earn at least 95 cents per dollar invested in the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Incorrect Answers:
B: This is the description of the schedule performance index.
C: This is not a valid statement about the project performance.
D: This is the description of the cost performance index.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
omankoman
3 weeks, 3 days ago
Selected Answer: A
A is right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago