Suggested Answer:B🗳️
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late. Incorrect Answers: A, C: These are not the valid answers, as there is just one day of float available for Activity H. D: There is one day of float still available for Activity H.