You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?
Suggested Answer:A🗳️
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email. Incorrect Answers: B: Many-to-many technique describes a conversation between many people. C: One-to-one technique describes a conversation between two people. D: A pull technique describes the recipients of the report "pulling" the information, such as from a Website.