Question #: 3
Topic #: 1
[All PMI-SP Questions]

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

  • A. Push technique
  • B. Many-to-many
  • C. One-to-one
  • D. Pull technique
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Incorrect Answers:
B: Many-to-many technique describes a conversation between many people.
C: One-to-one technique describes a conversation between two people.
D: A pull technique describes the recipients of the report "pulling" the information, such as from a Website.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
omankoman
3 weeks, 3 days ago
Selected Answer: A
A is right answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago