Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Suggested Answer:A🗳️
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used. Incorrect Answers: B: The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. C: Dependency determination identifies the order of the project work. D: Activity on the node places activities on circles within a network diagram. It is an example of the precedence diagramming method.