Suggested Answer:B🗳️
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Incorrect Answers: A: Estimating activity resources is dependent on the activity list, so this choice is not valid. C: Estimate activity durations are dependent on the activity list, so this choice is not valid. D: Sequencing the activities cannot happen until the activity list has been created.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.