An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

  • A. Remove the certification need from the project scope.
  • B. Escalate this to the project director for a resolution.
  • C. Review the process and remove the impediment.
  • D. Escalate this to the agile lead of the second team.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: C
C. Review the process and remove the impediment
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: C
This is the most aligned with the servant leader's role. Reviewing the process to identify and address the impediment involves understanding why the second team is delayed and finding a way to facilitate quicker certification. This proactive approach can help in solving the problem at its root.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...