Question #: 439
Topic #: 1
[All CAPM Questions]

A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule and the project team completed some project deliverables. The team is not colocated and some of the team members are former interns that were recently employed full time.

What is the most suitable project delivery method?

  • A. Adaptive project management
  • B. Linear project management
  • C. Extreme project management
  • D. Integrated project management
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
Adaptive project management is the most suitable approach due to its flexibility and ability to respond to changes. It allows the project manager to: Quickly assess the current project situation and identify areas for improvement. Leverage existing plans as a starting point but be prepared to modify them as needed. Build trust and collaboration with the team through open communication and iterative planning. Adapt to changing circumstances and incorporate feedback from stakeholders.
upvoted 1 times
...
1wheel
3 months, 2 weeks ago
Selected Answer: B
Detailed schedule - waterfall or linear
upvoted 1 times
...
David8989
4 months ago
Should be B -- a linear type of method because there is a detailed schedule and not a co located team
upvoted 1 times
...
ebbff63
4 months ago
Selected Answer: A
Ans:A B - pre-defined plan with minimal changes C,D - not suitable
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...