Exam PMP topic 1 question 1150 discussion

Actual exam question from PMI's PMP
Question #: 1150
Topic #: 1
[All PMP Questions]

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

  • A. Collaborate with the team to arrive at team ground rules and publish the rules to the team.
  • B. Request team members document their decisions independently and share with each other.
  • C. Escalate the team member's disruptive behavior to their functional manager.
  • D. Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tonybuivannghia
1 month, 2 weeks ago
Selected Answer: A
A is correct
upvoted 3 times
...
sidje
4 months ago
Selected Answer: U
En conclusion, en collaborant avec l’équipe pour établir des règles de base, le chef de projet crée un cadre de travail clair et respectueux qui aide à gérer les comportements perturbateurs de manière proactive et efficace.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...