A project manager is working on a large project in another country and realizes that only a few people from the project team are working on all of the releases. What should the project manager do to prevent this in the future?

  • A. Speak to the customer and add the issue to the issue log.
  • B. Document the risk register in the project charter.
  • C. Review user roles and update the team charter.
  • D. Involve the product owner to rewrite the user stories.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: C
C. Review user roles and update the team charter
upvoted 1 times
...
ELTIGANI
5 months, 3 weeks ago
Selected Answer: C
The word 'user' should be 'project team'.
upvoted 1 times
...
takaimomoGcup
6 months ago
Selected Answer: C
C is right answer.
upvoted 1 times
...
ompk
6 months, 1 week ago
The word "user" is confusing here however C is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...