During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality management plan and there is no reference to this component.
What should the project manager do next?
victory108
1 month, 3 weeks agoNA1234567
3 months agoKim222
3 months, 2 weeks agoKim222
2 months, 4 weeks agoAnitak
5 months, 1 week agoUppersquareCapital
6 months agoompk
6 months, 1 week ago