Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1290 discussion

Actual exam question from PMI's PMP
Question #: 1290
Topic #: 1
[All PMP Questions]

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality management plan and there is no reference to this component.

What should the project manager do next?

  • A. Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.
  • B. Keep running the manufacturing line because there are no quality specifications for this component.
  • C. Inform the project sponsor of the situation and wait for the sponsor to provide further directions.
  • D. Submit a change request to proceed with the replacement of the component and wait for further customer instructions.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: A
A. Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan
upvoted 1 times
...
NA1234567
3 months ago
Selected Answer: A
a because quality management plan has the component missing and it needs to be added
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: D
It cannot be documented in a quality control plan without special procedures.
upvoted 1 times
Kim222
2 months, 4 weeks ago
Sorry it is A
upvoted 1 times
...
...
Anitak
5 months, 1 week ago
Selected Answer: D When there is a significant change request or issue that arises, such as replacing a component due to reliability concerns, the project manager should follow the formal change management process. Submitting a change request ensures that the necessary approvals are obtained and the impact on the project is assessed and documented. This approach maintains control over the project scope, schedule, and costs, while also addressing the customer's concerns.
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: D
Submitting a change request follows the formal process for managing changes in a project. This ensures that any changes are documented, evaluated, and approved before implementation, which is essential for maintaining project integrity and traceability. The customer has identified a reliability issue with the component. Addressing this concern through a formal change request respects the customer's input and demonstrates responsiveness to their needs. The lack of reference to this component in the quality management plan indicates that there might be a gap in the documentation. Submitting a change request allows the project manager to formally address this gap by documenting the new requirement or specification for the component.
upvoted 2 times
...
ompk
6 months, 1 week ago
ChatGPT says D and I also beleive D since its a direct order from customer to stop prototyping and develop the new component so The project manager has to submit a change request as per customer's request
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...