A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
Amirov
3 weeks, 3 days agovictory108
1 month, 3 weeks agosidje
4 months agoKhoiCX
5 months, 4 weeks agoUppersquareCapital
6 months agoUppersquareCapital
6 months agokevzzz
6 months agoompk
6 months ago