A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

  • A. Draft a contract change with the desired scope changes and send it to the client for approval.
  • B. Forward the client's request to management as a change request to get formal approval.
  • C. Finish the current monthly release as it was planned and replan for the future months.
  • D. Document the information in the meeting minutes and share it with the project stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: D
D. Document the information in the meeting minutes and share it with the project stakeholders
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: D
In this situation, the project manager has received new information from the client about desired changes in milestones and outcomes. The first step should be to ensure that all stakeholders are on the same page regarding these changes. This means documenting the new requirements and ensuring they are communicated clearly to all relevant parties before any formal actions are taken. On the other hand, Option B might be necessary after the new requirements have been documented and discussed with stakeholders. The immediate priority is to document and communicate the new requirements, not to seek approval before this has been done.
upvoted 2 times
...
LNX_RM_Admin
6 months ago
Selected Answer: D
Document the information
upvoted 1 times
...
kevzzz
6 months ago
Selected Answer: B
The newly desired milestones and outcomes is a change in the project. The change requires approval.
upvoted 2 times
...
ompk
6 months, 1 week ago
I believe B is the first thing to do after confirming with the client to modify the scope change
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...