Question #: 444
Topic #: 1
[All CAPM Questions]

A new project manager has been assigned to an ongoing project. What will the project manager use to identify the responsibilities of the stakeholders in the project?

  • A. Responsible, accountable, consult, and inform (RACI) chart
  • B. Charter
  • C. Responsibility assignment matrix (RAM)
  • D. Stakeholder matrix
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A RACI chart (Responsible, Accountable, Consulted, Informed) is the most effective tool for identifying and clarifying the roles and responsibilities of stakeholders in a project. It clearly outlines who is responsible for completing a task, who is ultimately accountable for the task, who needs to be consulted before decisions are made, and who needs to be informed about the task's progress.
upvoted 1 times
...
ebbff63
4 months ago
A- RACI chart
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...