Exam PMP topic 1 question 1264 discussion

Actual exam question from PMI's PMP
Question #: 1264
Topic #: 1
[All PMP Questions]

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

  • A. User stories
  • B. Product backlog
  • C. Product roadmap
  • D. Business requirements document
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 3 weeks ago
Selected Answer: B
B. Product backlog
upvoted 1 times
...
kevzzz
6 months, 1 week ago
Selected Answer: B
The product backlog encompasses the entire project scope. It serves as a long-term, prioritized list of all features, enhancements, and fixes necessary for the product.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...