A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

  • A. Perform stakeholder engagement.
  • B. Perform integrated change control.
  • C. Update the quality management plan.
  • D. Update the risk management plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: B
Integrated Change Control includes identifying and engaging stakeholders, so B is correct.
upvoted 1 times
...
Kim222
1 month, 1 week ago
Selected Answer: A
It's A. Stakeholders must be identified and audit resources consulted.
upvoted 2 times
...
kevzzz
4 months ago
Selected Answer: B
The three main objectives of a change control process are, Analyzing the process and making corrective and preventive changes to stop recurring issues in a project. Ensuring the change requests are aligned with the project management plan.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...