A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
A.
Escalate to the project management office (PMO) and request a solution for the requirements.
B.
Allow the project team to decide what is the most appropriate requirement to follow.
C.
Negotiate a common agreement with the involved stakeholders regarding the requirements.
D.
Prioritize other items for the team and deal with the conflicting requirements later.
C. Negotiate a common agreement with the involved stakeholders regarding the requirements
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
2 weeks, 5 days ago