Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1155 discussion

Actual exam question from PMI's PMP
Question #: 1155
Topic #: 1
[All PMP Questions]

A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.

What should the project manager have done to prevent this?

  • A. Implemented the authorization in the first iteration
  • B. Reviewed the compliance requirements with stakeholders
  • C. Deployed to production after the first iteration
  • D. Planned smaller iterations to review the results more often
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 5 days ago
Selected Answer: B
B. Reviewed the compliance requirements with stakeholders
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...