Exam PMI-RMP topic 1 question 223 discussion

Actual exam question from PMI's PMI-RMP
Question #: 223
Topic #: 1
[All PMI-RMP Questions]

A project that was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up, the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

  • A. Risk management plan
  • B. Code of regulations
  • C. Project contracts
  • D. Risk register
  • E. Lessons learned registers from analogous projects
Show Suggested Answer Hide Answer
Suggested Answer: CDE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
1 month ago
Selected Answer: ADE
I think RMP is essential in order to continue with the initial plan although some parts had changed. Project contract information will be in the Risk Register and the PM will review it for Procurement Plan. Anything that will be worth to check, I assume it would be in the Risk register already.
upvoted 1 times
MikeMarlo
1 month ago
Sorry, ACD more accurate
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago