You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

  • A. Quality control
  • B. Kill point
  • C. Phase review
  • D. Audit
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sergey_k
2 months, 1 week ago
C. Phase Review. PgMP 5th Edition. p.115: 'Phase gate reviews are reviews at the end of a phase in which a decision is made whether or not to continue to the next phase, continue with modification, or end a program or program component"
upvoted 1 times
...
LuanND
4 months ago
Selected Answer: B
The term “kill point” is used in project management to determine whether the project should stop work or move to the next phase.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.