At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
victory108
2 weeks, 5 days agoKim222
2 months, 3 weeks agoUppersquareCapital
6 months agosidje
6 months, 1 week ago