Question #: 1172
Topic #: 1
[All PMP Questions]

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event. What should the project manager do first?

  • A. Use the contingency fund.
  • B. Update the risk register.
  • C. Prepare a change request.
  • D. Follow the risk response plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
2 weeks, 2 days ago
Selected Answer: D
D. Follow the risk response plan
upvoted 1 times
...
Kim222
2 months, 2 weeks ago
Selected Answer: D
due to an anticipated event
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...