Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

  • A. Review assumptions and constraints around risks.
  • B. Apply an iterative approach to risk identification.
  • C. Determine the likelihood and impact of the risks.
  • D. Develop the risk response plans for identified risks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Amakancn
1 month ago
Selected Answer: B
Applying an iterative approach to risk identification ensures that new risks are consistently identified and incorporated into the risk register, enabling the team to manage risks proactively and maintain project success.
upvoted 1 times
...
MikeMarlo
7 months, 1 week ago
Selected Answer: D
Next thing to do is to Develop some plans for the present risks that we have in the Project. In order, it will be: D, B, A, C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago