Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 193 discussion

Actual exam question from PMI's PMI-RMP
Question #: 193
Topic #: 1
[All PMI-RMP Questions]

A new project manager has been assigned to work on an ongoing project. When checking the project documentation, the project manager realizes the risk register items do not comply with the contracted scope. The project manager wants to use an objective method to determine the key project risks and develop response plans.

What action should the risk manager propose?

  • A. Hire a risk expert to perform a PESTLE evaluation.
  • B. Review the lessons learned from other projects.
  • C. Ask the team to perform a Monte Carlo analysis.
  • D. Ask the team to perform an earned value analysis.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
TheAWSGuru
2 months, 1 week ago
Selected Answer: A
A is the right answer
upvoted 1 times
...
MikeMarlo
4 months ago
Selected Answer: C
Risk assessment is done in Quantitative Analysis in order to determine the potential risks that a project has. In this case we can use EMV, Sensitivity Analysis, Monte Carlo simulations, etc. Hire >> never an option Lessons Learned >> useful for insights and context, not to analyze information EVA >> comparison actual schedule/cost vs baselines
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...