Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1330 discussion

Actual exam question from PMI's PMP
Question #: 1330
Topic #: 1
[All PMP Questions]

A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests.

Which two actions should the project manager take until the approval is received? (Choose two.)

  • A. Hire a vendor with the required expertise and infrastructure to complete the testing.
  • B. Stop testing immediately and escalate the issue to senior management for a decision.
  • C. Allow testing to continue for the complete duration as the policy may not apply to ongoing projects.
  • D. Update the project risk checklist to consider licensing and approvals for risk identification.
  • E. Reallocate the testing resources to complete testing early before the policy takes effect.
Show Suggested Answer Hide Answer
Suggested Answer: DE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tonybuivannghia
1 month, 1 week ago
Selected Answer: DE
D an E are correct.
upvoted 2 times
...
Saurav6233
3 months, 3 weeks ago
B does not make sense as there is still time for the policy to get implemented. Why stop the testing immediately.
upvoted 3 times
...
Saurav6233
3 months, 3 weeks ago
Selected Answer: DE
There is no concern highlighted with the current testing team, so hiring a vendor does not add value. C makes sense but pending effort is of 4 weeks but time left is 2 weeks for the possible compliance to come in play. Hence D and E would be the right answer. The new policy is expected in 2 weeks. Why stop testing immediately. So B does not make sense.
upvoted 2 times
...
takaimomoGcup
4 months ago
Selected Answer: BD
I agree. B and D.
upvoted 1 times
...
UppersquareCapital
4 months ago
Selected Answer: BD
Given that non-compliance with new regulations can lead to significant legal and financial repercussions, it is prudent to halt the testing and seek guidance from senior management. They can make an informed decision on how to proceed, considering the legal implications and organizational policies. Furthermore, Update the project risk checklist to consider licensing and approvals for risk identification. This action ensures that the project incorporates the new risk related to government policy changes. By updating the risk checklist, the project manager can better manage and mitigate similar risks in the future, ensuring that the project remains compliant with all regulatory requirements. These actions prioritize compliance with impending regulations and proactive risk management.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...