A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests.
Which two actions should the project manager take until the approval is received? (Choose two.)
victory108
1 month, 2 weeks agotonybuivannghia
3 months, 2 weeks agoSaurav6233
6 months agoSaurav6233
6 months agotakaimomoGcup
6 months agoUppersquareCapital
6 months, 1 week ago