Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1324 discussion

Actual exam question from PMI's PMP
Question #: 1324
Topic #: 1
[All PMP Questions]

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager do to address this situation?

  • A. Negotiate with the project sponsor immediately and establish a new project charter.
  • B. Modify the project management plan and get approval from relevant stakeholders.
  • C. Issue a change order to the change control board (CCB) and rebaseline the schedule.
  • D. Add more resources to recover the schedule without making changes to the baseline.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 2 weeks ago
Selected Answer: B
B. Modify the project management plan and get approval from relevant stakeholders
upvoted 1 times
...
d370e49
2 months, 1 week ago
Selected Answer: C
The answer is C, this follows proper channels. Step B is inefficient and doesn't resolve the issue.
upvoted 1 times
...
Kim222
2 months, 4 weeks ago
Its clearly B
upvoted 1 times
d370e49
2 months, 1 week ago
It's clearly not!
upvoted 1 times
...
...
omankoman
5 months ago
Selected Answer: B
B is the answer.
upvoted 2 times
...
UppersquareCapital
6 months, 1 week ago
Selected Answer: B
Modifying the project management plan involves a thorough analysis of the current schedule, identifying the reasons for delays, and developing a realistic plan to get back on track. This ensures that any adjustments are based on a solid understanding of the project's needs and challenges. In addition, by getting approval from relevant stakeholders, the project manager ensures that all key parties are aware of the changes and are on board with the new plan. This helps maintain transparency and secures the necessary support for implementing the adjustments. Modifying the project management plan and seeking stakeholder approval aligns with good project governance practices. It ensures that changes are formally documented and authorized, maintaining the integrity of the project management process.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...