In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.
How should the project manager handle this situation?
A.
Continue work and ask the product owner to assess the changes and add/remove the stories as needed in the backlog.
B.
Ask the product owner to add new changes to the bottom of the backlog in order to handle the modifications as a change request.
C.
Review the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project.
D.
Ask a business analyst to assess the changes and then add/remove the stories in the backlog and prioritize them by business value.
Review the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project.
This option ensures that the team addresses the changes immediately and integrates them into the current iteration in a way that maintains compliance and aligns with the updated product definition. It involves the product owner and the team reassessing and reprioritizing the iteration backlog, ensuring that the project remains on track and meets the necessary legal requirements.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 3 weeks agoUppersquareCapital
6 months, 1 week ago