A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.
How should the project manager handle this situation?
victory108
1 month, 3 weeks agoKim222
2 months, 3 weeks agosidje
3 months, 3 weeks agoParamak
4 months, 1 week agomartinx84
4 months, 2 weeks agoPmpjune152024
5 months, 2 weeks agoELTIGANI
5 months, 3 weeks agoUppersquareCapital
6 months, 1 week ago