Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1256 discussion

Actual exam question from PMI's PMP
Question #: 1256
Topic #: 1
[All PMP Questions]

In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final scope of the requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two.)

  • A. Establish a governance committee to review the contract delivery.
  • B. Provide alternatives to scope change at specific project phases within the contract.
  • C. Tier the contract for fixed and agile components.
  • D. Limit the number of iterations for development in the contract.
  • E. Require that only internal resources be utilized for this project.
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
sidje
1 month, 1 week ago
Selected Answer: BD
B et D
upvoted 1 times
...
ELTIGANI
3 months, 2 weeks ago
Selected Answer: CD
incorporating controls to tier the contract and limit iterations provides a structured yet flexible approach to managing the development of the core component under agile practices while safeguarding project profitability.
upvoted 1 times
...
UppersquareCapital
4 months, 1 week ago
Selected Answer: CD
Tiering the contract for fixed and agile components (Option C) and limiting the number of iterations for development (Option D) are the most effective controls for managing development costs and ensuring the profitability of the project while allowing for the flexibility needed in agile practices.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...