A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.
What should the project manager do?
victory108
1 month, 3 weeks agoAnhHN11
2 months, 3 weeks agoKim222
2 months, 4 weeks agotonybuivannghia
3 months, 2 weeks agokevzzz
6 months agoompk
6 months, 1 week agoUppersquareCapital
6 months, 1 week ago