A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.
What should the project manager do?
sblivia
3 days, 18 hours agovictory108
6 months agoAnhHN11
6 months, 4 weeks agoKim222
7 months agotonybuivannghia
7 months, 3 weeks agokevzzz
10 months, 1 week agoompk
10 months, 2 weeks agoUppersquareCapital
10 months, 2 weeks ago