An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.
What should the project manager do?
victory108
1 month, 3 weeks agod370e49
2 months, 1 week agoAKTDEEN
3 months, 1 week agoELTIGANI
5 months, 3 weeks agoLNX_RM_Admin
6 months agoUppersquareCapital
6 months, 1 week ago