Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1232 discussion

Actual exam question from PMI's PMP
Question #: 1232
Topic #: 1
[All PMP Questions]

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

  • A. Communicate the task assignments to the team members in a clear manner.
  • B. Confirm that the agile coach has made the task assignments clear.
  • C. Verify that the team members have made the task assignments clear.
  • D. Verify that the product owner has made the task assignments clear.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week ago
Selected Answer: A
This one is A. Task assignments should be clear, and if they are not, the PM should communicate that through means of scrum cards, etc.
upvoted 1 times
...
AKTDEEN
1 month ago
A As the project manager, ensuring clear communication of task assignments is crucial to prevent overlapping work and confusion among team members. While agile teams are typically self-organizing, the project manager can facilitate clarity and coordination by reinforcing clear communication channels and confirming that everyone understands their responsibilities. This approach helps maintain productivity and alignment within the team.
upvoted 1 times
...
ELTIGANI
3 months, 2 weeks ago
Selected Answer: C
Agile team is self-organizing
upvoted 1 times
...
LNX_RM_Admin
3 months, 4 weeks ago
Selected Answer: C
Manifesto Agile: Self-organizing teams choose how best to accomplish their work
upvoted 1 times
...
UppersquareCapital
4 months ago
Selected Answer: C
This approach encourages the team to take responsibility for their tasks and improves communication within the team, which is a fundamental aspect of agile practices. On the other hand, The product owner is responsible for the product backlog and ensuring the team works on the right tasks to deliver value, but they typically do not assign tasks directly to team members.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...