A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
Which document should the project manager update first to document this change?
Nimitto
1 month agovictory108
2 months, 4 weeks agoAnhHN11
3 months, 3 weeks agoBStub30
4 months, 1 week agoc8ee0e6
5 months, 2 weeks agokevzzz
6 months, 3 weeks agoompk
7 months agoUppersquareCapital
7 months, 1 week ago