Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1227 discussion

Actual exam question from PMI's PMP
Question #: 1227
Topic #: 1
[All PMP Questions]

A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.

Which document should the project manager update first to document this change?

  • A. Schedule baseline
  • B. Scope baseline
  • C. Risk register
  • D. Cost baseline
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nimitto
1 day ago
Selected Answer: A
Talks about adding more time explicitly, hence Schedule Baseline.
upvoted 1 times
...
victory108
1 month, 4 weeks ago
Selected Answer: A
A. Schedule baseline
upvoted 1 times
...
AnhHN11
2 months, 3 weeks ago
Selected Answer: C
C is correct.
upvoted 1 times
...
BStub30
3 months, 1 week ago
Selected Answer: A
The question mentions a delay in permits which is a scheduling issue. It makes no mention of risks or possible denials of permits. This means the schedule baseline would need to be updated and not the risk register since the risks arent increased.
upvoted 1 times
...
c8ee0e6
4 months, 2 weeks ago
Selected Answer: A
A is correct.
upvoted 1 times
...
kevzzz
5 months, 3 weeks ago
Selected Answer: A
Baselines would be updated with any significant change, the CCB already approved the change, the SME's have already submitted the Risk as a reality and followed the register so now the project schedule needs to be re-baselined.
upvoted 1 times
...
ompk
6 months ago
Option A is correct. Since the primary change involves adjusting the project schedule to account for potential delays, the schedule baseline should be updated first. This document defines the approved version of the project schedule, which includes start and finish dates for project activities. The agreed-upon additional time for permits needs to be reflected here.
upvoted 2 times
...
UppersquareCapital
6 months, 1 week ago
Selected Answer: C
The initial concern raised by the stakeholder and the reassessment by SMEs both pertain to potential risks associated with legal permits. The risk register is the primary document where all identified risks, their assessments, and planned responses are recorded. Once the risk register is updated, subsequent documents such as the schedule baseline (if the mitigation affects the timeline) and potentially the cost baseline (if the additional time has cost implications) should also be updated accordingly. However, the first and foremost document to update in response to a reassessed and mitigated risk is the risk register.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...