A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs) reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.
Which document should the project manager update first to document this change?
sblivia
3 days, 18 hours ago7579ad3
2 months, 2 weeks agoNimitto
4 months agovictory108
6 months agoAnhHN11
6 months, 4 weeks agoBStub30
7 months, 2 weeks agoc8ee0e6
8 months, 3 weeks agokevzzz
10 months agoompk
10 months, 1 week agoUppersquareCapital
10 months, 2 weeks ago