This graph describes the current performance of a project in relation to cost and schedule. What should the project manager do to bring the project back on track?
A.
Review project schedule because the project is under budget and behind schedule.
B.
Review project scope because the project is under budget and ahead of schedule.
C.
Review project schedule and cost because the project is over budget and behind schedule.
D.
Review project cost because the project is over budget and ahead of schedule.
You need to look at for the entire 6 weeks not just the last week.
For the Cost:
3 weeks < 1
2 weeks = 1
1 week > 1
Overall is over budget.
For the Schedule:
3 weeks = 1
3 weeks < 1
Overall is behind schedule.
So the answer is C
A CPI above 1 is good ( Under Budget ) , Below 1 is Bad ( Over Budget )
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 3 weeks agoKim222
2 months, 4 weeks agoLNX_RM_Admin
6 months agokevzzz
6 months, 1 week agoSunshine2022
6 months, 1 week agoUppersquareCapital
6 months, 1 week agoBlessedone
6 months, 1 week ago