Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1105 discussion

Actual exam question from PMI's PMP
Question #: 1105
Topic #: 1
[All PMP Questions]

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

  • A. Initiate a risk response strategy from the risk register.
  • B. Perform a detailed assessment to analyze the impact.
  • C. Reject the changes as the project is in the final stages.
  • D. Use schedule compression methods to alter the critical path.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
martinx84
1 month, 2 weeks ago
Selected Answer: B
B - Perform a detailed assessment
upvoted 1 times
...
sidje
4 months, 1 week ago
Selected Answer: B
Selon le PMBOK après avoir identifié un problème il faut ensuite l'analyser afin de déterminer la meilleure réponse à appliquer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...