A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
A.
Initiate a risk response strategy from the risk register.
B.
Perform a detailed assessment to analyze the impact.
C.
Reject the changes as the project is in the final stages.
D.
Use schedule compression methods to alter the critical path.
Selon le PMBOK après avoir identifié un problème il faut ensuite l'analyser afin de déterminer la meilleure réponse à appliquer.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
3 weeks, 6 days agomartinx84
3 months, 2 weeks agosidje
6 months, 1 week ago