Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1113 discussion

Actual exam question from PMI's PMP
Question #: 1113
Topic #: 1
[All PMP Questions]

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component managed by an external vendor. How should the project manager address the team member’s concern?

  • A. Implement fast tracking to reduce the impact of the delay on the sprint.
  • B. Ask the team member to provide details to address the issue with the vendor.
  • C. Ask the team member to resolve the issue independently to minimize further delays.
  • D. Update the communications management plan to prevent future reoccurrence.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: B
B. Ask the team member to provide details to address the issue with the vendor
upvoted 1 times
...
sidje
6 months, 1 week ago
Selected Answer: B
Selon le PMBOK après l'identification du risque il faut ensuite l'analyser
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...