During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component managed by an external vendor. How should the project manager address the team member’s concern?
A.
Implement fast tracking to reduce the impact of the delay on the sprint.
B.
Ask the team member to provide details to address the issue with the vendor.
C.
Ask the team member to resolve the issue independently to minimize further delays.
D.
Update the communications management plan to prevent future reoccurrence.
Selon le PMBOK après l'identification du risque il faut ensuite l'analyser
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
3 weeks, 3 days agosidje
6 months, 1 week ago