Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1021 discussion

Actual exam question from PMI's PMP
Question #: 1021
Topic #: 1
[All PMP Questions]

An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?

  • A. Assess consolidated project plans for dependencies, gaps, and continued business value
  • B. Delegate the review of dependencies to the project sponsor and resource manager
  • C. Schedule a daily interproject review to track the progress of each project plan and their dependencies
  • D. Ask the project management office (PMO) to review the project plan dependencies
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
9RedFox_JB
3 weeks, 4 days ago
Selected Answer: A
seems most logical. to have it documented in one place gives you time and possibility to evaluate and asses everything.
upvoted 1 times
...
517f9da
4 months, 1 week ago
Selected Answer: A
A. Assess consolidated project plans for dependencies, gaps, and continued business value Assessing consolidated project plans allows the project manager to identify and analyze dependencies, gaps, and the continued business value, enabling proactive risk management and coordination among interdependent projects.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...