An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?
A.
Assess consolidated project plans for dependencies, gaps, and continued business value
B.
Delegate the review of dependencies to the project sponsor and resource manager
C.
Schedule a daily interproject review to track the progress of each project plan and their dependencies
D.
Ask the project management office (PMO) to review the project plan dependencies
A. Assess consolidated project plans for dependencies, gaps, and continued business value
Assessing consolidated project plans allows the project manager to identify and analyze dependencies, gaps, and the continued business value, enabling proactive risk management and coordination among interdependent projects.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
9RedFox_JB
3 weeks, 4 days ago517f9da
4 months, 1 week ago