A project is being planned to deliver a proof of concept to evaluate technology compatibilities. The business and project stakeholders are having difficulty agreeing on what should be included in the final product.

What should the project manager do?

  • A. Include all stakeholders in the creation of the project charter.
  • B. Determine a clear distinction between business and technology benefits.
  • C. Include the technology suppliers in the creation of the business case.
  • D. Determine the root cause of their inability to determine the project scope.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month, 1 week ago
Selected Answer: D
D. Determine the root cause of their inability to determine the project scope. => Understanding Conflicts Facilitating Discussion Scope Clarity While including stakeholders in the project charter or involving technology suppliers may be helpful, understanding the underlying reasons for the disagreements will provide a more solid foundation for moving forward effectively.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: D
D. Determine the root cause of their inability to determine the project scope
upvoted 1 times
...
martinx84
4 months, 3 weeks ago
Selected Answer: D
Determine root cause
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
D. Determine the root cause of their inability to determine the project scope Determining the root cause of their inability to define the project scope helps identify the underlying issues, facilitating a more focused and effective resolution, and ensuring that all stakeholders' concerns are addressed properly.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...