Exam PMP topic 1 question 939 discussion

Actual exam question from PMI's PMP
Question #: 939
Topic #: 1
[All PMP Questions]

During user acceptance testing, a project sponsor asks the project manager to add a couple of features. To meet the firm go-live date, the project team will need to work overtime.

What should the project manager do?

  • A. Submit an emergency change request and assign tasks to the team.
  • B. Request approval for overtime and a bonus to deliver on time.
  • C. Inform the sponsor that the project team cannot commit to more work.
  • D. Consult with the project team and provide options to the sponsor.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
5 days, 15 hours ago
Selected Answer: D
D. Consult with the project team and provide options to the sponsor
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: D
D. Consult with the project team and provide options to the sponsor. Explanation: Consulting with the project team ensures that their input and capacity are considered before making any commitments. Providing options to the sponsor allows for a balanced discussion about the feasibility of adding new features, potential impacts on the timeline, and the team's ability to handle additional work, ensuring an informed decision can be made.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...