During user acceptance testing, a project sponsor asks the project manager to add a couple of features. To meet the firm go-live date, the project team will need to work overtime.
What should the project manager do?
A.
Submit an emergency change request and assign tasks to the team.
B.
Request approval for overtime and a bonus to deliver on time.
C.
Inform the sponsor that the project team cannot commit to more work.
D.
Consult with the project team and provide options to the sponsor.
D. Consult with the project team and provide options to the sponsor.
Explanation: Consulting with the project team ensures that their input and capacity are considered before making any commitments. Providing options to the sponsor allows for a balanced discussion about the feasibility of adding new features, potential impacts on the timeline, and the team's ability to handle additional work, ensuring an informed decision can be made.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
5 days, 15 hours ago517f9da
6 months, 1 week ago