A project manager is reviewing the documents for closing a phase when the customer calls to say that the project is not generating any value for the company. What should the project manager do?
A.
Wait to close the project until the customer is satisfied.
B.
Validate the project scope, objectives, and outcomes with the customer.
C.
Analyze which activities will generate the most value for the project.
D.
Perform a cost-benefit analysis for the project.
B. Validate the project scope, objectives, and outcomes with the customer.
Explanation: By validating the project scope, objectives, and outcomes with the customer, the project manager can ensure that there is a mutual understanding of the project's goals and whether they align with the customer's expectations. This helps identify any gaps or misunderstandings and allows for adjustments to improve the project's value to the customer.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 3 days agoKim222
2 months, 2 weeks ago517f9da
6 months, 1 week ago