Exam PMP topic 1 question 910 discussion

Actual exam question from PMI's PMP
Question #: 910
Topic #: 1
[All PMP Questions]

A project manager has been working on a critical project to transform an organization's operations. The project manager had successfully completed four sprints when the innovation director was replaced. The new director placed a hold on the project until a new strategy can be put in place.

What should the project manager do first?

  • A. Discuss the vision and possible impacts with the new director.
  • B. Review the risk management plan from previous projects with the new director.
  • C. Escalate to the project sponsor to remove the project hold.
  • D. Seek approval from the new director to replace the current contingency budget.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 4 days ago
Selected Answer: A
A. Discuss the vision and possible impacts with the new director
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: A
A. Discuss the vision and possible impacts with the new director. Explanation: Engaging the new director in a discussion about the project vision and potential impacts helps ensure alignment with the new strategy and addresses any concerns, paving the way for informed decision-making and possibly resuming the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...