Actual exam question from PMI's PMP
Question #: 1211
Topic #: 1
[All PMP Questions]

A leader from project B consistently reaches out to a team member in project A for assistance. What should project A's project manager do?

  • A. Tell project A's team member to ignore project B's leader.
  • B. Talk with project B's leader to discuss possible impacts to both projects.
  • C. Allow project B's leader to continue building relationships.
  • D. Ensure project A's team member can finish the work committed to project A.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: B
B. Talk with project B's leader to discuss possible impacts to both projects
upvoted 1 times
...
Sunshine2022
6 months, 2 weeks ago
Selected Answer: B
Project B is looking for assistance with their project and Project A may have some answers they needed. Without Project A’s help, Project B will be impacted. But with continuing assistance by Project A, the Project A team could risk of delaying and disrupting their work also. In hindsight to resolve any issue escalating and for both projects not to be impacted any further, is for Project A Project Manager to seat down and discuss with Project B Leader to come to term and work together harmoniously and collaboratively. Therefore, the answer is B.
upvoted 1 times
...
kevzzz
6 months, 2 weeks ago
Selected Answer: B
As the PM you address the issue head on and in a nice way, discuss the possible impacts to both projects.
upvoted 1 times
...
ompk
6 months, 2 weeks ago
I think its D, Since they project B member is "consistently" approaching the project A member which could arise risk of delaying or disrupting A's work.
upvoted 1 times
...
nicknamesdx
6 months, 3 weeks ago
Selected Answer: B
I think b is correct
upvoted 1 times
...
UppersquareCapital
6 months, 3 weeks ago
Selected Answer: D
The key action is to ensure that the team member remains focused on completing project A's tasks while handling any external requests or collaboration in a manner that doesn't compromise project A's commitments or timeline. This approach supports professionalism, effective time management, and maintains a positive working relationship with colleagues from other projects.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...