During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the required IT system. What should the project manager do?
A.
Fast track this dependency to avoid delaying the project.
B.
Perform Integrated Change Control.
C.
Ask IT to prioritize the needed system to meet the schedule.
D.
Include the dependency in the project schedule.
The Project manager should include the dependency in the project schedule to effectively manage and track the project's progress and dependencies. This proactive approach enables better project planning and risk management
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 4 weeks agoUppersquareCapital
6 months, 3 weeks ago