Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1206 discussion

Actual exam question from PMI's PMP
Question #: 1206
Topic #: 1
[All PMP Questions]

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the required IT system. What should the project manager do?

  • A. Fast track this dependency to avoid delaying the project.
  • B. Perform Integrated Change Control.
  • C. Ask IT to prioritize the needed system to meet the schedule.
  • D. Include the dependency in the project schedule.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 month, 4 weeks ago
Selected Answer: D
D. Include the dependency in the project schedule
upvoted 1 times
...
UppersquareCapital
6 months, 3 weeks ago
Selected Answer: D
The Project manager should include the dependency in the project schedule to effectively manage and track the project's progress and dependencies. This proactive approach enables better project planning and risk management
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...