Exam PMP topic 1 question 985 discussion

Actual exam question from PMI's PMP
Question #: 985
Topic #: 1
[All PMP Questions]

During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract end date. The contract is clear about the expiration of the service.

How should the project manager address this situation in order to close the project?

  • A. Escalate the request to the functional manager to approve the additional service hours.
  • B. Issue a change request and activate the formal change control process to address the situation.
  • C. Accept the client’s proposal to use the service until the additional hours are exhausted.
  • D. Deny the request and include it in lessons learned documentation for the next contract renewal.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: B
B. Issue a change request and activate the formal change control process to address the situation
upvoted 1 times
...
517f9da
7 months, 2 weeks ago
Selected Answer: B
Pretty straightforward but you can also use process of elimination. Other options don't make sense. B. Issue a change request and activate the formal change control process to address the situation. Explanation: Using the formal change control process ensures that any modifications to the project scope or contract are documented, reviewed, and approved in an official capacity. This approach maintains project integrity and contract compliance.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago