The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
A.
Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.
B.
Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.
C.
Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control.
D.
Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.
Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome Explanation : The project manager should determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome. This approach will help to resolve the conflicts and misunderstandings among stakeholders, which will ensure a smooth start and completion of the project.
D
As per PMBOK, To navigate stakeholder conflicts and ensure project success, the project manager should prioritize clear communication, stakeholder engagement, conflict resolution, scope clarification, risk mitigation, change management, and quality assurance. These strategies foster collaboration, manage expectations, and keep the project on track from start to finish.
Adigun
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 month, 4 weeks ago8001750
6 months, 3 weeks agoAditech
7 months, 2 weeks ago