Exam PMP topic 1 question 1198 discussion

Actual exam question from PMI's PMP
Question #: 1198
Topic #: 1
[All PMP Questions]

A project leader is assigned to a new project and is asked to assemble an effective five-member agile team. If the project leader has no restrictions, which team should they choose?

  • A. A team whose members have more general aptitudes and can collaborate on different tasks
  • B. A team whose members work independently and are the best subject matter experts (SMES)
  • C. A team whose members have more general aptitudes but like to work individually
  • D. A team whose members have different skill sets and are spread out geographically
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 5 days ago
Selected Answer: A
A. A team whose members have more general aptitudes and can collaborate on different tasks
upvoted 1 times
...
kevzzz
6 months, 1 week ago
Selected Answer: A
"general aptitudes and can collaborate on different tasks" you want this as part of your team.
upvoted 1 times
...
Sunshine2022
6 months, 1 week ago
Selected Answer: A
B refer to an I-Shape person. While C refer to a T-Shape person. In an ideal world you would need a combination to be in your team. D seem to address that combination; however, the geographical location of the team does provide a wide pool of expertise but in a practical scenario a collocated team is a better approach. A does also provide that combination. The collaborate on different tasks on the question suggest that they are working together in a collocated environment. Therefore, the answer is A.
upvoted 1 times
...
ompk
6 months, 1 week ago
Chatgpt says D if no restrictions then This option aligns with the principles of agile development. Having members with diverse skills ensures that the team can handle various aspects of the project effectively. Additionally, geographic diversity can bring different perspectives and approaches to problem-solving.
upvoted 1 times
...
Aditech
7 months, 1 week ago
A As per PMBOK, when assembling an effective five-member agile team for a new project, the project leader should prioritize creating a well-rounded team with diverse skills and expertise. This includes roles such as the Product Owner, Scrum Master, Software Developer, UX/UI Designer, and Quality Assurance Engineer. This composition aligns with agile principles and practices, fostering collaboration, communication, and successful project delivery. Adigun
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...