A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
A.
Encourage collaboration on a daily basis, facilitating different communication channels.
B.
Distribute a project newsletter that includes any project changes and required project information.
C.
Meet daily with the project team and include a monthly report on the risks and issues.
D.
Send out daily emails with the project status and task lists to all team members.
A
In conclusion, according to the PMBOK, to ensure collaboration and awareness of ongoing changes in a hybrid project, the project manager should establish clear communication channels, hold regular meetings, encourage open communication, utilize project management tools, provide ongoing training and support, document changes, regularly update stakeholders, and facilitate cross-functional collaboration among team members. These practices promote effective collaboration and communication, ensuring project success.
Adigun
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108