An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A.
Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.
B.
Create all of the stories just for the next sprint and skip the epics until the next sprint.
C.
Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.
D.
Create the epics at a high level for the requirements and begin grooming sessions.
D coz timeline is strict, can't wait for complete backlog to be ready Plus the mandate is there from Govt so all stories are to be completed. There is no prioritization based on business value needed.
D. Create the epics at a high level for the requirements and begin grooming sessions.
Creating high-level epics provides a structured overview of the requirements, which can then be broken down into more detailed user stories during backlog grooming sessions. This approach ensures that the team has a clear understanding of the project's scope and priorities while allowing for iterative refinement and prioritization of work according to business value.
The answer is C because
This option aligns with agile principles by breaking down the work into manageable stories and prioritizing them according to business value. It ensures that the team has a clear understanding of the work to be done and can start delivering value immediately.
C. Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.
Because prioritization of product requirement to meet the mandate in 6 months
D
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
Adigun
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 5 days agoKim222
2 months, 3 weeks agoKim222
2 months, 2 weeks agoNA1234567
2 months, 3 weeks agoccfdeaa
3 months agogaren22
3 months, 4 weeks agoAzharmak
4 months, 1 week agoompk
6 months, 1 week ago52d1fe0
6 months, 3 weeks agoAditech
7 months, 1 week ago