During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project. What should the project manager do?
A.
Update the contingency plan to take this issue into account.
B.
Meet with the stakeholders to update the risk register and risk management plan.
C.
Study the new regulations with the team and evaluate if there is any impact on the project variables.
D.
Review the procurement documentation and modify requirements as needed.
C
In conclusion, according to the PMBOK, when faced with a change in government regulations during a project, the project manager should assess the impact, communicate with stakeholders, review and adjust the project plan, engage with regulatory authorities if necessary, and continuously monitor changes to ensure compliance. These steps help mitigate risks and ensure the project remains aligned with legal requirements and objectives.
Adigun
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
1 week, 5 days agoAditech
7 months, 1 week ago